Background
As part of developing new wells for the water company, we renewed our permit with the Central Texas Groundwater Conservation District (CTGCD). As part of this renewal, the CTGCD placed a new Special Withdrawal Limitation (SWL) on our permit reducing our production amount from the original 114.7 acre-feet/year to 42.54 acre-feet/year. The SWL was added out of CTGCD’s concern for the impact on nearby wells external to Whitewater Springs. The CTGCD’s limitation forces the water company to place a temporary moratorium on selling new meters until such time as the CTGCD removes or increases the volume in the Special Condition.
To help better illustrate why the water company must place a moratorium on selling meters, here is some information the board of directors considered in making this decision:
The temporary moratorium on water meter sales has been lifted due to PUC requirements. The below information illustrates why the WSWSC will need to apply Stage IV restrictions to members to keep usage below the Special Withdrawal Limitation.
- The 42.54 acre-feet/year amount in gallons is 13,861,720 gallons.
- Water production for Whitewater Springs in 2024 was 13,413,550 gallons.
- Currently there are 160 active water taps and 40 inactive water taps
- When all 40 inactive water taps become active it is projected that total water production will be 14,757,075 exceeding the Special Condition by nearly 1 million gallons.
Moving Forward
This development is obviously distressing to our community. There are several actions the water company is pursuing to increase or remove this Special Condition:
We are working with our engineering company – BBA to prove that the modeling methodology does not predict water levels of the aquifer in the Whitewater Springs area and to suggest better modeling approaches.- We have submitted an additional study to the CTGCD that refutes the accuracy of the mandatory modelling methodology. CTGCD is currently evaluating the study.
- We are investigating CTGCD’s legal authority to reduce a longstanding water permit that conflicts with the TCEQ and PUC’s mandates regarding service to our community.
If you already have a water meter, this temporary moratorium will only impact you if the community water use exceeds the Permitted Special Condition. As previously mentioned, we are working to increase or remove the Special Condition so that a mandatory usage reduction is not required. What you can do as a landowner:
- You have the right to inform the CTGCD of your concerns with this new requirement. This may include written communication or addressing the CTGCD board at their meetings.
- Take actions to reduce your water usage, including minimizing or eliminating water usage for irrigation. Natural landscapes are a great way to reduce usage.
- Obtain a rainwater collection system. In some ways, rainwater is more guaranteed in this area than well water. A rainwater collection system can be a good hedge in the event that the Trinity Aquifer begins to show signs of weakness. The large amount of unregulated development in this area is cause for concern on this front.
- You may NOT drill your own water well in Whitewater Springs. The CCRs prohibit any private well from being drilled within 1,800 feet of any of the previously identified well lot locations. These lot locations are throughout the community as listed in the CCRs.
Resources
While the CTGCD actions are disappointing, the water company is doing what it can to increase its ability to produce water for the community. Hopefully this information is helpful to you. If you have any questions or concerns, the following contacts may be of assistance:
WSWSC – PermitQuestions@wswsc.org
Mitchell Sodek – General Manager CTGCD – sodek@centraltexasgcd.org
Reno Lamb – Precinct 3 Director CTGCD – pct3@centraltexasgcd.org
FAQs
That is not a simple question. The best thing would be to contact a company that sells these systems to analyze your needs and can size a system for this area.
Some pertinent information for our area:
- Our Rainfall average is 30 inches with a low of 16 inches and a high of 46 inches over the last 13 years
- For every 1,000 square feet of roof area 1 inch of rain will result in about 623 gallons of water collected. So for example: If you have a 2,400 sf single story house with a 600 sf garage you have about 3,000 sf of roof area. In an average year you’d expect to collect 30 inches rain * .623 gallons/Inch rain/sf * 3,000 sf = 56,070 gallons.
- The average person in Whitewater Springs uses 100 – 200 gallons per day depending on time of year and irrigation needs. The full year average ends up at about 150 gallons per day or 54,750 gallons per year.
- On a year when we don’t achieve our average rainfall it is fairly likely you’ll come out of the winter with a full tank. That plus what is collected during the year should cover an average household.
- If water collection runs short there is the possiblity of trucking in water albeit at a higher rate than from the water system.
Here is the main language that creates a restriction for all of Whitewater Springs land area:
”Section 29: Restriction on Well Spacing.” Notwithstanding the provisions of Section
12 of Article IV. Section 28 of Article IV, Sections 6 and 7 of Article IX or Section 7 of
Article XI, or any other provision herein to the contrary, the following restriction shall apply with respect to drilling wells anywhere within the Project by an individual Owner, the Association or any other person: a.) no water well of any kind may be drilled within 1,800 feet of the perimeter boundary of any· Designated Well Lot, as identified on Exhibit “B” attached to this Amendment. The only party entitled to enforce the provisions of this Section 29 shall be a “PWS Well Designator” which shall be: a.) LCRA, or any· successor retail water service provider to the Project or b.) any· party who has a written agreement with LCRA or any successor retail water provider to the Project allowing the party to construct a public water supply well on a Designated Well Lot for subsequent dedication to LCRA or any successor retail water provider to the Project as part of LCRA ‘s or any successor retail water provider to the Projects community water system serving the Project. Any Owner of a Designated Well Lot may file an instrument in the Official Property Records of Burnet County removing such lot from the list of Designated Well Lots. Upon recordation of such an instrument such lot shall be released from the requirements of this Section 29 for all purposes. This restriction shall apply and shall be enforceable through any remedy at law or equity by a PWS Well Designator
regardless of whether or not a public water supply well is completed or operational on a Designated Well Lot.”
EXHIBIT B
Lot 88 of WHITEWATER SPRINGS, SECTION ONE, as recorded in Cabinet 2, Slides 1088-111 A. Plat Records of Burnet County, Texas.
Lot 136, WHITEWATER SPRINGS, SECTION TWO, as recorded in Cabinet 2, Slide 120D-124A. Plat Records of Burnet County, Texas.
Lot 17 3, WHITEWATER SPRINGS, SECTION TWO, as recorded in Cabinet 2, Slide 120D-124A, Plat Records of Burnet County, Texas.
Lot 213. WHITEWATER SPRINGS, SECTION TWO. as recorded in Cabinet 2, Slide I20D-124A, Plat Records of Burnet County, Texas.
Lot 216, WHITEWATER SPRINGS, SECTION TWO, as recorded in Cabinet 2, Slide 120D-124A, Plat Records of Burnet County, Texas.
Lot 205A, A REPLAT OF LOT NOS. 204 & 205, WHITEWATER SPRINGS, SECTION TWO, as recorded in Cabinet 2, Slide 127A, Plat Records of Burnet County, Texas.
Lot 325, WHITEWATER SPRINGS, SECTION THREE, as recorded in Cabinet 2, Slides 148Al49C, Plat Records of Burnet County, Texas.
Lot 356, WIIITEWATER SPRINGS, SECTION THREE, as recorded in Cabinet 2, Slides 148A-149C, Plat Records of Burnet County, Texas.
Lot 370, WHITEWATER SPRINGS, SECTION THREE, as recorded in Cabinet 2, Slides 148A-149C, Plat Records of Burnet County, Texas.
Lot 502B, A REPLAT OF LOT NOS. 501-504, 506-507, 511-512, AND 519, WHITEWATER SPRINGS, SECTION FIVE, as recorded in Cabinet 2, Slides 172C-173A, Plat Records of Burnet County, Texas.
Lot 512B, A REPLAT OF LOT NOS. 501-504, 506-507, 511-512, AND 519, WHITEWATER SPRINGS, SECTION FIVE, as recorded in Cabinet 2, Slides 172C-173A, Plat Records of Burnet County, Texas.
Lot 516, WHITEWATER SPRINGS, SECTION FIVE, as recorded in Cabinet 2, Slide 154C-155A, Plat Records of Burnet County, Texas.
Lot 605, WHITEWATER SPRINGS, SECTION SIX, as recorded in Cabinet 2, Slides 174A-175C, Plat Records of Burnet County, Texas.
Lot 606, WHITEWATER SPRINGS, SECTION SIX, as recorded in Cabinet 2, Slides I74A-I75C, Plat Records of Burnet County, Texas.
Lot 655, WHITEWATER SPRINGS, SECTION SIX, as recorded in Cabinet 2, Slides 174A-175C, Plat Records of Burnet County, Texas.
Fourth Amendment Declaration of Covenants, Conditions and Resolutions for Whitewater Springs Subdivision
Yes you may. If you decide to implement a rainwater collection system to replace all of your needs you could sell your meter to someone planning to build in Whitewater Springs.
Contact PGMS if you want to make a transfer to another resident
Absolutely not! This is a temporary moratorium. There are two possible developments that may allow us to sell more meters. By revising the modeling with the district we may be able to justify more acre-feet of production. There are limits to this as it is expensive to do this modeling. The CTGCD may also determine that they are in conflict with the PUC and TCEQ requirements that we serve our CCN. More on that as our legal counsel explores this further.
The temporary moratorium has now been lifted. Meters are now available for purchase.
Well 4 increases how much we can physically pump out of the ground, but it does not change how much the permit from the district allows us to pump.
Well 4 is important to keep us at a safe operating level for the number of meters supported by the water system.
The short answer is no effect. If we don’t sell any new meters then we won’t have to increase water production. New meter fees are used to fund new wells and infrastructure to increase water production. No new meters = no need to increase production. The charges on your water bill are used to pay for operation and maintenance of the existing water system which will remain stable if we aren’t adding new meters.
The WSWSC will now be required to sell meters. This will eventually cause usage to hit the Special Withdrawal Limitation requiring members to reduce their usage.